One hour after the project owner's closing date for bids, the BSDQ accesses the submitted bid information and can thus produce the report.
Only bidders who have submitted for the project will have access to the tabulation report in their specialty.
H-1 Access to tenders by the BSDQ
One (1) hour after the deadline for recipient contractors to file tenders to the project owner, the BSDQ has access to the tenders filed and all the information they contain, in accordance with the procedure established by the BSDQ for the use of the TES. It then compiles the tenders and makes them available to the persons mentioned who may obtain a copy, such as the project owner, the architect, and the engineer.
H-2 Compilation of tenders
The BSDQ compiles a list of tenders filed for each regulated specialty. This list provides information on the names of the tenderers, the price of their tenders if it is a lump sum, the tender security attached to it, if applicable, the names of the recipient contractors to whom it is addressed and the names of those who have taken possession of it, and any other information deemed relevant by the BSDQ that may be contained in the tender or its schedules. This compilation may be consulted by all tenderers mentioned, regarding the specialty concerned, in accordance with the procedure established by the BSDQ for the use of the TES.
However, the compilation may not be consulted by tenderers who have withdrawn their tenders in accordance with the provisions of Chapter F of this Code.
When the price indicated is not a lump sum, the compilation does not provide the tender price; the names of the tenderers are then listed in alphabetical order.
Recipient c ontractors w ho have t aken p ossession o f one o r m ore t enders m ay c onsult, f or t he specialties concerned, a compilation containing only the names of the tenderers, in alphabetical order.